Rugani Carrots 2MW Generator Synchronized Project

Solution Overview

Installation Date 2020
Location Tarlton
Installation Duration 5 Weeks
Client Goal The client needed back up power, as they would lose a large amount of revenue during down time due to power outages.

Project Info

Generators 4x 500 kVA Volvo Generator Set
Project Type 2MW Synchronized Back up Generator System
Build Custom Built with super silent canopies
Other Specs
  • 20000l Automated refueling System
  • Deepsea Control System with Webnet Interface

CMH GROUP

Solution Overview

Grid-Tied Solar PV.

Installation Date 2020
Location Hatfield Pretoria
Installation Duration 2 weeks
Client Goal To reduce carbon emissions and reduce reliance on Eskoms grid.

Project Info

System Size 16.2 kWp
Inverters Used Solis
Annual Yield 25.78 MWh
Installation Type Commercial Grid-Tied
Annual kWh \ kWp \ Year 1591.5

Signal Hill

Solution Overview

Installation Date 2020
Location Western Cape
Installation Duration 1 Week
Client Goal The client was looking for a solution to assist them with load shedding problems they are having. As they are a brewery, they cannot afford to be offline whilst they should be brewing beer, as this is a process that needs to run for several hours.

Project Info

Generators
  • 1 x 400 kVA Baudouin Generator set

VEB M.E

Solution Overview

Installation Date  2020
Location Boksburg
Installation Duration 2 weeks
Summary The solar plant is the first 5G Solis inverter installed in South Africa, this is a Full in house engineered design and constructed project, with full council approval, lightning risk assessment reports and implementation.

Project Info

System Size 91.8 kWp
Inverters Used 5g Solis
Annual Yield 155.8 MWh
Installation Type Commercial Grid-Tied
Annual kWh / kWp Year 1697.2

Bag Babe

Solution Overview

Installation Date 2020
Location Pretoria
Installation Duration 3 Days
Client Goal  Back up Power

Project Info

Generators
  • 1 x 200 kVA Volvo Generator set

Eez Wel Engineering

Solution Overview

Installation Date 2020
Location Randburg
Installation Duration 2 Days
Client Goal Back up Power

Project Info

Generators
  • 1 x 200 kVA Perkins Generator set

Workshop Electronics

Solution Overview

Installation Date 2020
Location Chamdor
Installation Duration 1 Month
Client Goal Provide back-up power for mobile testing stations for the South African Municipalities

Project Info

Generators 8 x 60 kVA custom built generators

Restonic

Solution Overview

Installation Date 2015
Location Booysens
Installation Duration 1 week
Client Goal Customer had a unique problem to consolidate the backup supply from gensets from different sites to the newly built factory. The new building where the customer had moved to, was supplied by an 11 kV ring-main feed. Our 4 existing Cummins generators and 2 new 500KVA Scania generators where all synchronised and run through a step-up transformer, whereby it supplies the full capacity of the factory as well as providing seamless control of the multiple generators when the load requirement is low.

Project Info

Generators
  • 2 x 500 kVA Scania Generator sets
  • 3 x 250 kVA Cummins Generator sets
  • 1 x 200 kVA Cummins Generator sets

Off-Grid Ladismith

Solution Overview

Installation Date 2019
Location Ladismith
Installation Duration 2 weeks
Client Goal To go off the grid and to become completely self-sustainable

Project Info

System Size 18 kWp
Inverters Used 15 kVA Victron Quattro
Battery Capacity 91 kWh
Battery Specification Pylontech
Installation Type Off-Grid

RSB Timbers

Solution Overview

Installation Date 2019
Location Chamdor
Installation Duration 4 weeks
Client Goal To reduce their reliance on the national grid and reduce their carbon footprint

Project Info

System Size 297 kWp
Inverters Used Solis
Annual Yield 482.4 MWh
Installation Type Commercial Grid-Tied
Annual kWh \ kWp \ Year 1624.3